Practical 5: Running a Sprint: Daily Scrum and Burndown

Lab Practical SE-401 Software Engineering 7 min read Updated 8 Nov 2026
On this page
  1. 1. Objectives
  2. 2. Word bank
  3. 3. Background
  4. 4. Before you start
  5. 5. Time plan (50 minutes)
  6. Part A: Warm-up: who does it?
  7. Part B: Predict: will this sprint finish?
  8. Part C: Find the flaw
  9. Part D: Graded tasks (10 marks)
  10. Part E: Post-lab questions
  11. Marking rubric
  12. Submission

How you work today

Work in your project team on your Trello board from Practical 2. Task 3 (the burndown) is done by each student on their own computer. Marks are given to each student.

1. Objectives

By the end of this practical you will be able to:

  • Set up your team as a Scrum team (Product Owner, Scrum Master, Developers) with a clear sprint goal.
  • Run and record daily scrums on your board.
  • Draw a sprint burndown chart in a spreadsheet and read it: ahead, behind, blocked.

2. Word bank

Word

Simple meaning

Real-world example

sprint goal

one sentence that says what value this sprint will deliver

"A student can order and the kitchen can see it."

daily scrum

15-minute daily planning meeting for the Developers

a 10-minute WhatsApp call at 9 p.m.

impediment

anything that blocks progress

no internet in the lab

burndown chart

chart of story points left on each day of the sprint

24 points on day 0, 0 on day 10

ideal line

straight line from the total to zero, showing steady progress

24 - 2.4 × day

3. Background

In Lecture 05 you learned the Scrum roles, artifacts and events. Today your team runs a sprint on its Trello board and tracks it with a burndown chart.

Daily scrum record. Each member writes a short comment on one card they are working on: Y (yesterday), T (today), B (blockers). Example: "Y: finished menu screen. T: start order screen. B: none."

Burndown chart. x-axis = day of the sprint; y-axis = story points left. The ideal line falls by the same amount every day: total ÷ number of days. In a 24-point, 10-day sprint it falls 2.4 points per day, so the ideal value on day d is 24 − 2.4 × d.

Real-world example: the canteen's day of cooking

The canteen starts the day with 24 orders to cook. The manager writes on a board how many are left every hour.

If the number stays the same for two hours, something is wrong (gas finished, a cook is absent). A burndown chart shows a software team the same thing.

4. Before you start

1. Open your team's Trello board from Practical 2.

2. Open Excel or Google Sheets on your own computer for Task 3.

5. Time plan (50 minutes)

Time

What you do

0:00-0:05

Teacher: quick demo of a daily-scrum comment and a burndown chart

0:05-0:15

Parts A, B and C (on paper)

0:15-0:23

Task 1: Scrum team and sprint goal on the board

0:23-0:33

Task 2: three daily scrums recorded on the board

0:33-0:45

Task 3: burndown chart in a spreadsheet and answers

0:45-0:50

Teacher checks; start Part E (finish at home)

Part A: Warm-up: who does it?

Write PO (Product Owner), SM (Scrum Master) or Dev (Developers) for each action.

(a) Decides that the payment story comes before the meal-rating story.

(b) Asks the department to fix the lab internet that is blocking the team.

(c) Splits the "place order" story into tasks and writes the code.

(d) Stops the daily scrum when it reaches 15 minutes.

Part B: Predict: will this sprint finish?

A team plans 15 points for a 5-day sprint. Points left: day 0 = 15, day 1 = 14, day 2 = 13, day 3 = 12.

(a) What is the ideal value on day 3?

(b) At its current speed, will the team finish on day 5? What should it do?

Part C: Find the flaw

Each item has ONE main problem. Name it.

(1) In the daily scrum the team lead asks each person for a status report, then spends 20 minutes solving a database problem with one developer.

(2) Sprint goal: "Finish tasks 1 to 12."

(3) The burndown line goes up on day 4, and nobody knows why.

Part D: Graded tasks (10 marks)

Task

Level

What you build

Marks

T1

Easy

Set up the Scrum team and sprint goal

3

T2

Medium

Record three daily scrums

3

T3

Challenge

Draw and read a burndown chart

4

Total

10

T1 Set up the Scrum team and sprint goal (3 marks · Easy)

1. Add a card at the top of Sprint 1 - To Do called Scrum Team. In its description write who is Product Owner, Scrum Master and Developers, with one reason for each choice.

2. Add (or update) the Sprint 1 goal card: one sentence of user value and the planned points, e.g. "Goal: a student can order and the kitchen can see it. 20 points."

3. Give every Sprint 1 card a due date on the last day of the sprint.

Sample: Scrum Team card

PO: Hira - she talks to the canteen manager every week.

SM: Bilal - organised and keeps time; he also develops.

Developers: Ali, Sana, Usman (and Hira, Bilal).

T2 Record three daily scrums (3 marks · Medium)

1. Run three short daily scrums for Day 1, Day 2 and Day 3 of the sprint (a few minutes each, standing at your desks).

2. Each day, every member writes one comment on a card they are working on, in the form "Day n - Y: ... T: ... B: ...", and moves the card if its status changed.

3. The Scrum Master adds an Impediments card and lists any blocker raised.

4. At the end of each day, write the points left in the Sprint 1 goal card (Day 0 = total).

Sample: Comment on the "Place an order" card

Day 2 - Y: built the cart screen. T: connect the Place order button. B: need the order data format from Ali.

Points left - Day 0: 20 · Day 1: 20 · Day 2: 18 · Day 3: 18

T3 Draw and read a burndown chart (4 marks · Challenge)

1. In a spreadsheet make three columns: Day (0 to 10), Ideal, Actual. Use this sprint: 24 points over 10 days. Actual points left: 24, 24, 21, 19, 19, 16, 12, 10, 6, 3, 0.

2. Fill the Ideal column with a formula: in cell B2 type the formula =24-2.4*A2 and copy it down.

3. Insert a line chart of Ideal and Actual against Day. Add a title and axis titles.

4. Answer: (a) On which days was nothing finished? (b) On day 5, is the team ahead or behind, and by how much? (c) Did the team finish? Was it ever ahead of the ideal line?

5. Attach a screenshot of your chart to the Sprint 1 goal card.

Sample: Expected spreadsheet (first rows)

Day | Ideal | Actual

0 | 24 | 24

1 | 21.6 | 24

2 | 19.2 | 21

5 | 12 | 16

Part E: Post-lab questions

1. How does a burndown chart help the Product Owner and the Scrum Master?

2. Your burndown is flat for two days. Give two possible causes and one action for each.

3. How is a daily scrum different from a status meeting with a manager?

Marking rubric

Task

Marks

Full marks when ...

T1 Set up the Scrum team and sprint goal

3

1 mark: correct roles with reasons

1 mark: sprint goal of user value with point total

1 mark: due dates on all Sprint 1 cards

T2 Record three daily scrums

3

1 mark: own three Y/T/B comments (individual)

1 mark: cards moved to match the comments

1 mark: Impediments card and points-left record

T3 Draw and read a burndown chart

4

1 mark: ideal column uses a formula

1 mark: correct line chart with titles

1 mark: answers (a) and (b)

1 mark: answer (c) and screenshot attached

Parts A, B, C and E are not marked separately; they prepare you for the tasks and the viva.

Submission

  • The teacher checks your board and your chart before you leave.
  • Upload to the LMS by the end of the day: the board link, a screenshot of the Scrum Team and Sprint 1 goal cards, and your burndown spreadsheet.
  • Copy your Scrum role, your three daily-scrum comments and your chart answers into the Lab Book (Practical 05 page).

← All SE-401 material